Skip to main content

Lower Pescadero Creek Multi-Objective
Management Plan and Designs

Key Project Statement

Waterways collaborated with the San Mateo Resource Conservation District (SMRCD) to develop a science-based management plan for the 3.2-mile stretch of the Pescadero Creek in the vital Pescadero-Butano watershed. Focused on enhancing ecological function, habitat, and addressing flooding concerns, the project included geomorphic assessments, hydraulic modeling, and sediment transport analysis. The resulting plan prioritizes 20 project concepts, with current efforts concentrated on habitat restoration and a coordinated flood control plan for the town site. 

The 81-mile Pescadero-Butano watershed is the largest coastal watershed between San Francisco Bay and Monterey Bay and contains one of the most important anadromous fish populations in central California. The San Mateo Resource Conservation District (SMRCD), one of the key stakeholders involved in resource planning in the watershed, hired Waterways to develop a science-based Lower Pescadero Creek Multi-Objective Management Plan for the 3.2-mile-long reach upstream of the Pescadero Lagoon, which flows through agricultural land and the town of Pescadero. In this reach – which includes numerous landowners and land use types including agricultural and residential land, schools, park lands, and the town of Pescadero – a better quantitative understanding of hydraulic and geomorphic processes was needed to support stakeholders in their coordinated efforts to reduce flooding and bank erosion while also enhancing the ecological function and habitat. The project involved assimilation of extensive past work; geomorphic assessment and mapping; developing a reliable calibrated hydraulic model; sediment transport analysis; and the development of a reach-scale Multi-Objective Management Plan for the stream corridor. 

BANK EROSION THREATENING PROPERTY IN TOWN REACH - 2019

BANK EROSION THREATENING PROPERTY IN TOWN REACH - 2023

The Multi-Objective Management Plan provides a concrete strategy for addressing the three primary objectives of reducing flooding impacts, reducing damage due to bank erosion, and improving in-channel habitat in lower Pescadero Creek. The Plan contains an overall, reach-scale strategy along with a prioritized set of 20 specific project opportunities within the lower Pescadero Creek corridor. The overall strategy is to develop projects that will supplement one another to address the primary management objectives in the parts of the study area in which each is most relevant. For example, flooding and bank erosion are considered to be problems primarily within the reach that includes the Pescadero town site, whereas these processes may not present problems, and could even be considered beneficial, in parts of the creek in which infrastructure is not affected. Additionally, whereas the Existing Conditions Characterization identified that a lack of wood in the channel is a primary detriment to habitat throughout the study reach, and especially downstream of the Pescadero town site, the hydraulic characterization found that wood jams can contribute to flooding in the town site in moderately large floods. The largest and highest priority project - a multi-objective project addressing bank erosion, flooding, and in-stream habitat involving numerous properties within the Pescadero Town Site - is currently in the design phase. 

Key Project Information

  • Client

    San Mateo Resource Conservation District

  • Services Provided

    Watershed/Geomorphic Assessments; Land Surveying; Hydrologic and Hydraulic Gauging, Modeling, and Analysis; River and Wetland Restoration Design; Civil Design; Construction

  • Project Manager